Our approach, developed over decades of experience, is fine-tuned to get the results you want.
We deliver concept-to-completion solutions, designed by temporary power specialists with access to the largest inventory of high-quality power generation and distribution equipment in North America.
From a wide range of diesel and natural gas generators to transformers, cable, light towers and more, our large rental fleet and extensive vendor network ensure we’ll have the temporary power equipment that your project requires — every time.
For nearly 20 years, we have been at work powering projects across Canada’s industrial sectors.
Select from this sampling of industries to learn how we can put our expertise to work for you.
VIEW ALLFrom our inception in 1998, we have been building our team on a foundation of excellence. Our team members’ passion, expertise and commitment are what have allowed us to grow into a national company with projects across Canada.
Click on the links to learn more about our history, our team or our career opportunities.
With so many moving pieces, large commercial construction projects require careful planning to stay on track. But even meticulously managed jobs aren’t immune to unexpected roadblocks. Equipment failure n general is a reality — one that can seriously impact a construction project’s budget and timeline.
That’s where Trinity Power comes in. Our quick response and project-centred temporary power solutions have saved many client ventures from significant delays and added costs. This was the case recently, when a client experienced an equipment failure at their construction site in Northern BC.
Founded over 70 years ago in Alberta, this client has grown into a North America-wide construction company with teams of experts operating across a wide variety of sectors, including mining, oil & gas, infrastructure, forestry, communications, and many more.
Despite their massive growth over the past 70 years, this client remains true to the values it was founded on: honesty, safety, giving back and delivering excellent work.
Our client was overseeing the re-development of a mall in Northern BC when the unexpected happened: one of the transformers powering the construction activities failed, leaving the site without adequate power.
The client had ordered core and coil replacements to repair the unit, but the lead time was going to be three to four months. In the meantime, the work had to continue. They called Trinity Power.
The Trinity team is no stranger to urgent equipment requests, so when this client called, we were able to move quickly and efficiently.
Thanks to our large inventory, we were able to source:
Within 24 hours, the team had prepped and loaded the equipment to be shipped from our Coquitlam location to the site.
We also handled all of the shipping logistics, including bringing in a crane to offload the 15,000 pound substation when it arrived on site.
Because of the Trinity team’s ability to source and ship the equipment so quickly, our client’s construction project was able to move forward, meeting target dates as originally planned.